The construction site will rest from 23.12.2022 to 15.01.2023.

Review

To date, there have been few complaints from residents about noise disturbance at night. The building owner has tried to talk to these people.

The lack of visibility at the crosswalk and the speed of cyclists are further problems in connection with the construction site. Solutions are being sought together with the traffic police. Various corrections are being made, e.g. removal of the signboard due to restricted visibility, possibly installation of signs and mirrors, etc. Unfortunately, many road users do not obey the traffic rules.

Outlook

in January 2023 night work is expected again, but it will be only a few hours. On January 16, 2023, excavation will begin. This will last approximately one year until probably December 2023. Archaeological finds are not expected.

Fotos: Roland Lässer
Source text: Minutes Meeting 08.12.2023 Client and DDPS

Weitere relevante Artikel

Alle ansehen
  • Da steht er, der Ausserrhoder-Böögg, und meint: ich lasse mich doch nicht von den Zürchern anzünden! Die Zürcher finden das „ausserrhodentlich“. Es zeichnet sich ab, dass der Böögg in den Gastkanton Appenzell Ausserrhoden reisen wird, um dort verbrannt zu werden.

    Continue reading
  • Das Zürcher Epizentrum der Adventszeit liegt unumstritten in unserem schönen Quartier. Am Donnerstag, 23. November 2023 öffnete das festliche und schmucke Wienachtsdorf auf dem Sechseläutenplatz seine Pforten. Bei besten Witterungsbedingungen fand das Spektakel bereits am ersten Tag einen grossen Zulauf an Gästen.

    Continue reading
  • The 19th Zurich Film Festival came to an end on Sunday evening, 08.10.2024. Despite the beautiful weather, it recorded 130,000 visitors. A total of 150 films were shown, 52 of which had their world or European premiere-

    Continue reading